1、電蒸汽鍋爐http://www.hbyuandong.com.cn/及其輔機、水處理設備等的安裝應符合設備制造廠(chǎng)的技術(shù)要求,設備基礎必須待設備到貨并與設計圖紙核對無(wú)誤后,方可施工。
Installation of electric steam boilers and auxiliary equipment, water treatment equipment, etc. shall comply with the technical requirements of equipment manufacturers, equipment foundation must be after the arrival of equipment and design drawings and check and correct, before construction.
2、電蒸汽鍋爐管道最高點(diǎn)放氣、最低點(diǎn)放水。
Electric steam boiler tubes deflate the highest point, the lowest point of water.
3、電蒸汽鍋爐管道安裝后的試壓驗收,按《工業(yè)金屬管道工程施工及驗收規范》進(jìn)行。
Pressure test after acceptance electric steam boiler pipe installation, according to the "industrial metal pipeline construction and acceptance of" conduct.
4、電蒸汽鍋爐http://www.hbyuandong.com.cn/鍋爐房?jì)人杏秒娫O備及蓄熱裝置等都應可靠接地。
Should be grounded electric steam boilers and boiler room all electrical equipment thermal storage devices.